Skip to main content

North Loop Transmission

Powering Brownsville's future. Discover how our new transmission line is boosting reliability and supporting growth.

BPUB is undertaking a comprehensive transmission infrastructure upgrade program to meet the demands of unprecedented load growth. With projected increases of 200+ megawatts over the next five years, BPUB is implementing strategic substation upgrades and new construction to ensure reliable electric service for residential and commercial customers.


Current System Status

Existing Infrastructure:

  • 15 substations operating at 138 kV
  • 50 miles of transmission lines
  • Ring system configuration for enhanced reliability
  • Peak historical load: 334 megawatts

Service Area:

All infrastructure serves the Brownsville city limits with connections to adjacent transmission service providers.

Load Growth Drivers

The rapid expansion of Brownsville’s electrical demand is expected to increase over the next five years and is driven by:

Residential Development

  • 124 MW of new load from subdivision developments concentrated in northern Brownsville
  • Multiple large-scale residential projects

Industrial/Commercial Growth

  • 90 MW of new industrial load commitments
  • Significant expansion near Port of Brownsville
  • Large individual loads ranging from 50-300 MW
  • Projected Total Impact

~500-600 MW total system peak load anticipated by 2030

  • Nearly double current peak capacity requirements
  • Sustained 2% annual growth rate plus new development
  • Strategic Solution: North Transmission Loop

To address concentrated growth north of the city, BPUB is developing a North Transmission Loop strategy that mirrors the successful ring system currently serving southern Brownsville.

Key Features:

  • New 138 kV transmission lines forming northern ring
  • Multiple new substation locations
  • Redundant power sources for all stations
  • Ability to tap into transmission for future growth

This infrastructure will enable BPUB to serve new loads efficiently while maintaining the redundancy standards that ensure continuous service even during equipment failures.

Project Stages

Stage 1: Loma Alta/Cipher Substation (Already Underway)

The Loma Alta rebuild serves as the critical first phase of the north loop strategy. Originally planned with two 28 MVA transformers, the project scope is being increased to accommodate two 50 MVA transformers (100 MVA total capacity) due to emerging large load opportunities. Some individual loads at the port exceed 100 MW, making this enhanced capacity essential.

Timeline: Quarter 3, 2028

  • Status: Design phase, equipment procurement initiated
  • Board Action Required: Approval to procure larger transformers

The complete north loop buildout will occur in phases as load materializes, and funding is secured.

Project Benefits

Grid Reliability

Creates redundant transmission pathways for improved reliability

Capacity Growth

Increases transmission capacity to support development

Power Quality

Improves voltage stability and power quality for customers

Future Ready

Positions infrastructure for continued community growth

Current Mitigation Projects

Ocelot Substation (New Construction)

Capacity: 60 MVA Timeline: Energization Q2 2026 Status: Construction underway New 138 kV substation serving the northern growth corridor. The first major component of the North Transmission Loop strategy.

Palo Alto Substation Upgrade

Capacity Addition: 28 MVA transformer Timeline: Completion Q1 2027 Status: Design and procurement phase Adding transformer capacity to existing station serving northern Brownsville residential areas. Critical for near-term subdivision development.

Waterport Substation Upgrade

Capacity Addition: 28 MVA transformer Timeline: Completion Q1 2027 Status: Design and procurement phase Expansion dedicated to Port of Brownsville industrial development. Supports logistics and manufacturing facilities.

Loma Alta Rebuild (Cipher Substation)

Capacity Addition: Up to 250 MVA (two 125 MVA transformers) Timeline: Completion Q3 2028 Status: Design phase, equipment procurement approved Complete rebuild of existing station with substantially increased capacity. Renamed "Cipher" upon completion. Located near Port of Brownsville to serve large industrial loads. Equipment specifications upgraded during design process to accommodate potential 50-100+ MW individual customers.

Airport Substation Rebuild

Capacity Addition: 56 MVA Timeline: Ongoing through 2026 Status: Demolition in progress Full rebuild of existing substation infrastructure. Current loads temporarily served by Strand mobile substation to maintain system flexibility during construction.